Friday, July 27, 2007

The frame is up!!!!!

Our house!!!! The family/kitchen, the entry, the garage and the family again, with our big doors










Sunday, July 22, 2007

Frame is delivered after a delay



We had a delay in that the electricity hadn't been connected, but now a few weeks later we have a frame delivered, hopefully they will get a start next week. At least the slab got to cure a bit longer

Saturday, July 7, 2007

We have a slab!




We now have a slab and our temp fencing!!!! Burbank also said we should have frames next week and gutters the week after!!!

Saturday, June 30, 2007

Pipes, a meter box and some big trenches

Full steam ahead! Burbank said we should have a slab next week too, then we will have to think about selling our house




Sunday, June 24, 2007

Site cut!

Well they've done the sit cut now, it's all moving forward!



Friday, June 15, 2007

A fence and a tap!

We have a fence, after a letter asking for us to "urgently" send approval, we negotiated a taller fence and agreed to have it done, even though we would prefer not to have the fence up for the start of our construction, we didnt want to disadvantage our new neighbours. The fence has been up nearly 2 weeks and their back fence and other side still aren't done, so I guess there really was an urgency lol



We also more recently have a tap! We have water, it's starting!!!!! YAY!!!!
We also got our final council approved plans and have sent them back.